How to Get a Certificate of Occupancy in Florida: 2026
Learn how to get a certificate of occupancy in Florida: the steps, documents, inspections, timelines, and tips to avoid common CO delays in 2026.

Key Takeaways
-
Before anything else, confirm which city or county building department controls your property, since application requirements, fees, and workflows differ across Florida jurisdictions.
-
Ask your building department whether you need a certificate of occupancy (new construction or change of use) or a certificate of completion (remodels, renovations, shell buildings), as the rule varies locally.
-
Before submitting, confirm every permit for the address, including trade permits, shows as finaled or closed, and that all fees are paid, since one open permit can stall the whole CO request.
-
Build a closeout package with the department's current checklist: CO application, permit number, final inspection records, required agency approvals, and as-builts or engineer letters if the work changed from the plans.
-
Under Florida Statute 553.791, when a qualified private provider is used, the building official generally has up to 10 business days (2 for single or two-family homes) to issue the CO or identify deficiencies after a complete request.
-
Do not occupy or use a building before the CO is issued, as this can cause problems with the building department, lenders, insurers, and buyers; ask about a temporary CO if partial use is needed.
You finished the build, the paint is dry, and the crew has finally packed up. Then someone asks the question that stops everything: "Do we have the CO yet?" If that sounds familiar, take a breath. You are in good company, and this is very doable.
If you have been wondering how do i get a certificate of occupancy in florida, the short answer is this. Finish the permitted work, pass every required inspection, collect the other agency approvals, close out your permits and fees, and then submit your local building department's CO request with the closeout documents it asks for. The details change from one city or county to the next, and that is where most people trip up.
In this friendly 2026 walkthrough, we will cover what a CO is, who issues it, the step-by-step process, the documents you will likely need, how long it takes, and what to do when something goes sideways. Whether you are a general contractor, a solar installer, a realtor, or a homeowner, you will leave with a clear game plan.

What Is a Certificate of Occupancy in Florida?
A certificate of occupancy, or CO, is the official document showing that a building or space is safe and compliant enough to be used for its intended purpose. In Florida, it is generally issued by the local building department or building official after construction is complete and inspections and other required approvals are satisfied.
Think of it as the finish line ribbon for your permit. Without it, you often cannot legally occupy a new building, open a business in a new space, or complete certain sales and financing steps.
CO vs. Certificate of Completion
Here is a wrinkle that surprises many people. Some jurisdictions issue a certificate of completion (CC) instead of a CO for certain projects. The City of Miami, for example, describes COs as applying to new construction or a change of use, and certificates of completion as applying to remodels, renovations, and shell buildings. Other places draw the line differently, so always confirm which document applies with the authority having jurisdiction.
| Document | Commonly Used For | Key Point |
|---|---|---|
| Certificate of Occupancy (CO) | New construction, change of use or occupancy classification | Allows the building or space to be used as approved |
| Certificate of Completion (CC) | Remodels, renovations, shell buildings in some jurisdictions | Confirms permitted work is finished and passed final inspection |
| Certificate of Use (CU) | Business operation in an existing space in some jurisdictions | Separate from a CO; often tied to zoning and business use |
If you are not sure whether you need a CO or a certificate of use, our guide on certificate of occupancy vs. certificate of use breaks it down.

Who Issues a Certificate of Occupancy in Florida?
There is no single statewide office that hands out COs. The local building department, or the building official for your city or county, is typically responsible. That means the application, documents, fees, and workflow can look very different in Tampa than in Naples or Miami.
One of the trickiest parts is figuring out who actually controls your address, especially near city lines. A property with a city mailing address can sometimes fall under county jurisdiction. Our guide to which Florida jurisdiction reviews your project can help, and our building department lookup tool is a handy starting point.
How to Get a Certificate of Occupancy in Florida: Step by Step
Here is the typical path from "we are almost done" to "we have our CO." Your local department may add or reorder a few items, but this sequence covers the heart of it.
- Identify the correct building department. Confirm whether your property falls under a city or county building department before you do anything else.
- Confirm CO or CC requirements. Ask which certificate applies to your project and what the closeout checklist looks like.
- Complete the permitted work. All work covered by the building permit, and any trade permits, needs to be finished.
- Pass all required inspections. That means the trade inspections (electrical, plumbing, mechanical, structural) and the final building inspection.
- Secure other agency approvals. Depending on the project, this may include fire, zoning, utilities, health, accessibility, or elevator sign-offs.
- Close related permits and clear fees. Every subcontractor or trade permit should be closed, corrections addressed, and outstanding fees paid.
- Submit the CO or CC request. Turn in the jurisdiction's application along with required closeout documents.
- Receive the certificate. Once it is issued, you can occupy or use the space as local rules allow.
Why Step 6 Trips People Up
Closing out permits sounds boring, but it is where many CO requests stall. A single open trade permit, an unpaid fee, or an unresolved correction can hold up the whole thing. Before you submit, check the online permit record for your address and make sure everything shows as finaled or closed.
If you want a quick look at what is still open, try our open permit search tool.
Documents You May Need for a Florida CO
Requirements are jurisdiction- and project-specific, so treat this as a typical list rather than a guarantee. Your building department's CO checklist is the final word.
- A completed CO or CC application
- Your permit number or permit card
- Approved final inspection records
- Contractor or architect certifications, where required
- Fire, zoning, utility, health, or accessibility approvals, where applicable
- Elevator or other specialty approvals for certain projects
- Proof that related permits are closed and fees are paid
- As-built drawings or engineer letters when the project changed during construction
That last item deserves a mention. If the finished building differs from the approved plans, the department may ask for documentation of what was actually built. Our article on what an as-built drawing is and when you need one explains how that works.
Inspections Before a CO Is Issued
Inspections are the backbone of the whole process. Which ones apply depends on your scope of work, but most projects look something like this.
| Inspection Type | What It Checks | Typically Needed For |
|---|---|---|
| Structural / framing | Load path, connections, framing per approved plans | New builds, additions |
| Electrical | Wiring, panels, grounding, devices | Most projects |
| Plumbing | Piping, fixtures, drainage | Most projects |
| Mechanical (HVAC) | Equipment, ducting, ventilation | Most projects |
| Fire / life safety | Alarms, sprinklers, egress, extinguishers | Commercial and some residential |
| Final building | Overall completion and code compliance | Nearly all CO and CC requests |
If a final inspection does not go your way, do not panic. It happens more often than people admit. We walk through the fixes in what to do when a Florida final inspection fails.
How Long Does It Take to Get a CO in Florida?
Honest answer: it depends on your jurisdiction, your project type, and how clean your closeout package is. There is no universal turnaround that applies to every request.
There is one important exception worth knowing. Florida Statutes section 553.791 sets a specific process when a fee owner uses a qualified private provider for building-code inspection services. After a complete request, a certificate of compliance, required government approvals, and payment of outstanding fees are submitted, the local building official generally has up to 10 business days to issue the CO or CC, or to identify deficiencies. For permits related to single-family or two-family dwellings, that window is up to 2 business days.
Please note that these statutory timelines apply to the private-provider process and should not be treated as a guarantee for every CO request. If you are curious how that route works, our piece on how Florida Statute 553.791 works for permits is a good read, and our private provider inspections service page shows how we put it to work.
What Does a CO Cost?
Fees vary widely by location. As one local example only, a Town of Palm Beach application lists a $75 minimum CO or CC permit fee plus an additional charge calculated per square foot. That is not a statewide fee schedule, so check your own department's current fee sheet before you budget.
Can You Occupy a Building Before the CO Is Issued?
Generally, no. Occupying or using a building before the required certificate is issued can cause trouble with the building department, lenders, insurers, and buyers. Some jurisdictions issue a temporary certificate of occupancy in limited situations, which allows partial or interim use while minor items are finished. Check with your local department before anyone moves in, and see our explainer on what a temporary certificate of occupancy is in Florida.
Common Reasons a CO Gets Delayed
After helping with permits across the state, the same few culprits show up again and again. Here is what to watch for.
- Open or expired permits. A forgotten trade permit can stop everything. See how to close an expired permit in Florida.
- Unpermitted work. Work done without a permit can trigger a hold on the CO. Our guide to 14 ways to clear a CO hold for unpermitted work shows the path forward.
- Failed or missing inspections. One missed inspection can ripple through the whole closeout.
- Missing agency approvals. Fire, zoning, or utility sign-offs that never got requested.
- Unpaid fees. Small balances can hold up an otherwise complete file.
- Plans that do not match what was built. This often calls for as-builts or an engineer letter.
When Does a Renovation or Change of Use Need a New CO?
A CO is commonly required for new construction. It may also be required when a change of use or occupancy classification occurs, such as converting a retail space to a restaurant or an office to a medical use. Some remodels and renovations get a certificate of completion instead.
Because this varies by jurisdiction, the safest move is to ask the building department early, ideally before you finalize plans. If your project involves a business moving into an existing space, you may also need a certificate of use, which we cover in do I need a certificate of use to open a business in FL.
Tips by Audience: What Matters Most to You
General Contractors
Build your closeout checklist into the project schedule from day one. Track every trade permit and inspection so nothing lingers open when it is time to request the CO. If you work across multiple counties, remember that each department has its own quirks.
Solar Companies
Most solar installs are finaled through the permit rather than a full CO, but new construction with solar, or projects tied to a larger build, may be part of a CO closeout. Keep your inspection sign-offs and documentation tidy. Our guide on speeding up solar permit expediting in Florida can help.
Realtors and Investors
A missing CO or an open permit can derail a closing fast. Check permit history early in your due diligence. Our article on whether you can sell a Florida house without a certificate of occupancy is worth bookmarking, and our realtor and closing support page explains how we help.
Homeowners
If you built or renovated, keep your permit card, inspection records, and any contractor paperwork in one folder. When it is time to request your CO or CC, having everything together makes the process far smoother. Our homeowner resources are a friendly place to start.
How a Florida Permitting Service Can Help
You do not have to do this alone. A permitting-services professional can help identify the correct jurisdiction and certificate type, coordinate permit closeout and inspections, assemble required documents, track outstanding approvals, and communicate with the building department on your behalf. Just be sure to confirm the provider's scope, and make sure licensed professionals perform any regulated work.
At 1 Contractor Solutions, we act as Florida's outsourced permitting department. We are not a construction contractor. We handle the paperwork, tracking, and plan review coordination across all 67 Florida counties, and our in-house drafting and engineering team means sealed drawings and as-builts do not depend on an outside consultant calling back. You can learn more on our Certificate of Occupancy service page and in our guide on how to get certificate of occupancy help in Florida.
Curious what others say about working with us? See what customers share when you visit us on Google — 1 Contractor Solutions.
A Quick Pre-Submission Checklist
Before you hit submit on that CO request, run through this list. It takes five minutes and can save weeks.
- Confirm every permit for the address, including trade permits, shows as finaled or closed.
- Verify all inspections passed and corrections are cleared.
- Gather agency approvals (fire, zoning, utilities, health, accessibility) if applicable.
- Pay all outstanding fees and confirm the balance is zero.
- Collect as-builts or engineer letters if the build differed from the plans.
- Download the department's current CO or CC checklist and match your package to it.
Final Thoughts: Cross the Finish Line with Confidence
Getting a CO is really about preparation. Know which jurisdiction controls your property, finish your inspections, close out permits and fees, gather your documents, and submit a clean package. When it all lines up, the process is far less scary than it sounds.
And if you hit a snag, whether that is an open permit, a failed inspection, or a hold you did not see coming, help is available. Our urgent permit rescue team steps in when closings and schedules are on the line. Ready to move your project across the finish line? Get a free quote and let us take the permit headache off your plate. You can also follow us on LinkedIn and follow us on Facebook for more Florida permitting tips, and our website marketing partner is Brain Buzz Marketing.
FAQs
How do I apply for a certificate of occupancy in Florida?
Start by confirming which city or county building department controls your property, then finish the permitted work, pass all inspections, close related permits, and submit that department's CO or certificate-of-completion request with its closeout documents. Every jurisdiction runs its own checklist, so ask for the current one before you submit.
What is the difference between a certificate of occupancy and a certificate of completion in Florida?
A CO is commonly used for new construction or a change of use, while some jurisdictions issue a certificate of completion for remodels, renovations, or shell buildings. The exact rule varies by city and county, so confirm with your local building department which one applies to you.
How long does it take to get a certificate of occupancy in Florida?
Timing varies by jurisdiction and project, and there is no single statewide turnaround. When a qualified private provider is used under Florida Statutes section 553.791, the building official generally has up to 10 business days (2 for single-family or two-family dwellings) after a complete request to issue the CO or identify deficiencies.
Can I occupy a building before the certificate of occupancy is issued?
Generally no, since occupying before the required certificate is issued can create problems with the building department, lenders, and insurers. Some jurisdictions allow a temporary CO in limited cases, so check with your local department before anyone moves in.
What documents do I need to get a certificate of occupancy in Florida?
Common items include a completed application, your permit number or permit card, approved final inspection records, contractor or architect certifications, and any required fire, zoning, utility, or accessibility approvals. Requirements are specific to your jurisdiction and project, so match your package to the department's current checklist.
We do this work every day across all 67 Florida counties. Call (866) 314-6931 and we will tell you what your situation actually requires — including when you do not need us.
Related services
Permit Facilitation & Filing
You have a crew scheduled, a client asking for dates, and a permit sitting somewhere in a queue you cannot see. We file it, w…
See the servicePlan Review Coordination
A permit in plan review is not one queue. On a commercial project it can be six queues, each with its own reviewer, its own c…