How Long Does a Building Permit Take in Miami?

City of Miami reviews take about 14 business days; Miami-Dade County, 24 hours to 10 days. Learn what really drives your permit timeline in 2026.

Published 2026-11-11 Updated 2026-11-1114 min read
How Long Does a Building Permit Take in Miami?

Key Takeaways

  • The City of Miami estimates about 14 business days for a first review cycle on a standard building permit, but this starts only after the application is accepted into ePlan review.

  • Unincorporated Miami-Dade County estimates 24 hours to 10 business days for initial plan review, and corrections resubmissions take another 24 hours to 10 business days.

  • Confirm which jurisdiction controls your property first, since the City of Miami, unincorporated Miami-Dade, and other municipalities like Coral Gables each run their own process and clock.

  • Miami-Dade County will not review plans until required upfront fees are paid, so confirm fee status the same day you submit to avoid unnecessary delays.

  • Published review estimates exclude application prep, correction rounds, outside-agency approvals, and fee payment, so plan your schedule around the full process rather than the first review alone.

  • Eligible small residential projects in the City of Miami may qualify for same-day Homeowner's Express Review if submitted by 10 a.m. with complete documents, but do not rely on it without confirming eligibility.

You have the plans, the crew is penciled in, and the client keeps asking one question: how long does a building permit take in Miami? If you have ever stared at a permit portal wondering why nothing has moved, you are in good company. Almost everyone who builds, remodels, or installs equipment in Miami-Dade County has felt that wait.

Here is the honest answer: it depends. The biggest factor is which jurisdiction controls your property. The City of Miami, unincorporated Miami-Dade County, and the county's other municipalities each run their own process on their own clock. The published numbers are also review estimates, not promises about when you will be holding an issued permit.

In this guide, we will break down the real timelines, explain what stretches them out, and share practical ways to keep your project moving. Whether you are a general contractor with a crew waiting, a solar company chasing approvals, a realtor trying to protect a closing, or a homeowner planning an addition, you will leave with a clearer picture of what to expect in 2026.

how long does a building permit take in miami

The Short Answer: It Depends on Your Jurisdiction

"Miami" can mean the City of Miami, or it can mean any of the many municipalities inside Miami-Dade County. Each municipality has its own building official and its own permitting process. Unincorporated Miami-Dade County uses the County's process. Before you estimate a single day on your schedule, confirm exactly where the property sits. That is not always obvious near city lines.

Once you know the jurisdiction, here is how the published estimates compare:

Jurisdiction Published Review Estimate What It Covers
City of Miami (standard building permit) About 14 business days First review cycle after the application is accepted into ePlan review
City of Miami (special permit) About 35 business days First review cycle for special permit applications
Unincorporated Miami-Dade County 24 hours to 10 business days Initial plan review, depending on permit type and complexity
Unincorporated Miami-Dade (corrections) 24 hours to 10 business days Review of resubmitted corrections
City of Miami Homeowner's Express Review Same-day possible Eligible small residential projects submitted by 10 a.m.

Notice what these numbers are and are not. They describe review time. They do not include the time it takes you to assemble a complete application, answer corrections, collect outside approvals, or pay fees and pull the permit. That gap between "first review" and "permit in hand" is where most schedules get surprised.

how long does a building permit take in miami

How Long Does a Building Permit Take in the City of Miami?

For a standard City of Miami building permit application, the City estimates roughly 14 business days for the first review cycle. That clock starts after your application is accepted and enters ePlan review, not the day you first upload documents.

Fourteen business days is about three calendar weeks. But a typical project involves more than one trip through review. If the reviewers leave comments, you respond, resubmit, and the plans go around again. Each additional cycle adds time.

What the City's Estimate Leaves Out

The City's first-cycle estimate does not account for:

  • Time spent preparing a complete, code-compliant application
  • Waiting for application acceptance before review begins
  • Responding to corrections and resubmitting
  • Additional review cycles after resubmission
  • Outside-agency approvals and impact-fee payments
  • Paying remaining fees and officially pulling the permit

This is why a project with a "14-business-day" review can easily take several weeks longer from start to finish. Plan your schedule around the whole journey, not just the first review.

Special Permits Take Longer

The City lists about 35 business days for the first review cycle of special permit applications. If your project falls into that category, the timeline is more than double the standard estimate, so confirm your permit type early.

How Long Does Miami-Dade County Take to Review Plans?

If your property sits in unincorporated Miami-Dade County, the County says initial plan review may take anywhere from 24 hours to 10 business days, depending on the permit type and how complex the project is. A simple scope may clear quickly, while a more involved set of plans may land closer to the 10-day mark.

If reviewers request changes, a review of your corrections (often called a "rework") can take another 24 hours to 10 business days after you resubmit.

Fees Come First

Here is a detail that trips people up: Miami-Dade County states that plans will not be reviewed until the required upfront fees are paid. If you submit and then wait for review, check that nothing is sitting unpaid. Once all disciplines approve the documents and the remaining fees are paid, the permit can be issued.

Can You Get a Same-Day Permit in Miami?

Sometimes, yes. The City of Miami offers Homeowner's Express Review for eligible small residential projects, and same-day approval is possible. The City says applications generally need to be submitted by 10 a.m., and the goal is to respond within one business day, with timing affected by completeness, corrections, weekends, and holidays.

Keep in mind a few caveats:

  1. Eligibility matters. Only certain small residential projects qualify.
  2. Documents must be complete. Missing items can derail a same-day review.
  3. Corrections have cutoffs. Resubmission deadlines apply.
  4. Some applications get moved. If your project does not fit, it may shift to regular review.

Express review is a great option when your scope truly fits. But do not build a tight schedule around it unless you have confirmed eligibility first.

The Real Timeline: From Idea to Issued Permit

Let's walk through a realistic sequence, because the permit clock is only one piece of the puzzle.

  1. Confirm the jurisdiction. Find out whether the City of Miami, unincorporated Miami-Dade, or another municipality controls your property.
  2. Prepare the plans. Depending on scope, this may include architectural drawings, structural plans, MEP plans, and a site plan.
  3. Assemble the application. Gather forms, owner and contractor information, product approvals, and any required surveys.
  4. Submit and pay required fees. The County will not begin plan review until upfront fees are paid.
  5. Wait for acceptance and first review. This is where the 14-business-day or 24-hour-to-10-day estimates apply.
  6. Answer comments. Address every reviewer note and resubmit.
  7. Secure outside approvals. Some projects need other agencies to sign off.
  8. Pay remaining fees and pull the permit. Only then can work legally begin.

Prep time at the front end and correction time in the middle are the two biggest swing factors. A clean, well-prepared submission can shave weeks off the total.

What Causes Building Permit Delays in Miami?

Most delays are not mysterious. They tend to come from a handful of predictable sources. Here is a quick look at the usual suspects and how to head them off.

Common Delay Why It Happens How to Prevent It
Incomplete application Missing forms, signatures, or documents keep the file from being accepted Use a checklist and verify completeness before submitting
Plan review comments Drawings do not match code or lack required detail Have plans prepared and sealed by professionals familiar with local requirements
Multiple review cycles Each resubmission restarts a review round Respond to every comment fully and precisely
Outside-agency approvals Environmental, water and sewer, or other sign-offs run on separate timelines Identify required approvals at the start and file in parallel
Unpaid fees Plans are not reviewed until upfront fees are paid Confirm fee status the same day you submit
Wrong jurisdiction Filing in the wrong place wastes time Verify the controlling jurisdiction before you file

Some projects also need approvals from other agencies, such as Miami-Dade County environmental or water and sewer departments, or impact-fee payments. These dependencies can add real time beyond the building plan-review estimate, so ask about them up front rather than discovering them mid-review.

Tracking Your Application So Nothing Slips

One of the easiest ways to protect your schedule is to watch your application like a hawk. You do not have to guess where things stand.

  • City of Miami: Use iBuild and ProjectDox to view status, review comments, and discipline-level progress.
  • Miami-Dade County: Use the County's Plans Status and Application Submittal Portal with your process number.

Check in regularly. If a discipline has approved and another is still pending, you will know exactly where the holdup is. If comments post, you can start on corrections the same day instead of days later. That kind of responsiveness is often the difference between a three-week review and a two-month saga. If a denial lands, our guide to denied permit help in Miami walks through how to fix and resubmit.

Is the Timeline Different in Miami Beach, Coral Gables, and Other Cities?

Yes, it can be. Because each municipality has its own building official and process, a permit in Coral Gables or Miami Beach does not follow the City of Miami's 14-day estimate or the unincorporated County's range. Each one publishes its own procedures, portals, and review practices.

The takeaway: never assume. Look up the specific building department that governs the address, and read its current process before you promise a client a date.

Tips for Different Readers

General Contractors and Design Trade Professionals

Your biggest lever is submission quality. Complete drawings, correct product approvals, and fast turnaround on comments keep you out of extra review cycles. If your team is stretched thin, outsourcing drafting, engineering, and permit tracking can free your crew to focus on building.

Solar Companies

Solar permits need code-compliant structural and electrical documentation. Missing or mismatched details are a classic reason for correction rounds. See our guide on ways solar companies get permits faster in Miami for practical ideas.

Realtors and Property Buyers

If a closing depends on legalizing work or clearing an open permit, time matters. Start the research early, and review resources like what a permit hold means in Miami so you can plan around it.

Homeowners and Residential Property Owners

Additions, remodels, and structural changes need properly prepared plans. If your project is a small residential scope, ask whether it might qualify for express review. For larger work, build extra weeks into your expectations.

Ways to Speed Things Up

You cannot control the reviewer's calendar, but you can control a lot about your own submission. Here are the moves that tend to matter most:

  • Submit a complete package the first time. Acceptance happens before review begins, so an incomplete file just burns days.
  • Use professionally prepared, sealed drawings. Clean plans draw fewer comments.
  • Pay upfront fees immediately. In the County, nothing is reviewed until they are paid.
  • Respond to comments fast and thoroughly. Half-answers trigger another round.
  • Track your status daily. Catch changes the moment they appear.
  • Line up outside approvals early. Do not wait until the building review finishes.

Some owners also explore a private provider route to shorten review time. Our article on private provider plan review in Miami explains how that option works, and how to speed up roofing permit approval in Miami offers trade-specific tips.

What If Work Was Already Done Without a Permit?

Sometimes the question is not "how long will a new permit take" but "how do we fix something that was built without one." That is a different path with its own timeline. If you are in that situation, start with after-the-fact permit requirements in Florida and the steps to legalize unpermitted work. And if you are navigating a denial or hold, who can rescue a denied building permit in Florida is a helpful read.

How 1 Contractor Solutions Can Help

At 1 Contractor Solutions, we act as an outsourced permitting department across all 67 Florida counties. We prepare plans, file the application, track it, work every reviewer comment, and carry the permit through approval and closeout. Our drafting and engineering are in house, with our own engineer sealing the work, so when a reviewer flags something, we fix it without waiting on an outside consultant. We also respond within 30 minutes, day or night. You can visit us on Google — 1 Contractor Solutions to see what our customers say, or follow us on LinkedIn and follow us on Facebook for Florida permitting updates. Our marketing partner, Brain Buzz Marketing, helps us share those insights with the community.

Final Thoughts: Plan for the Whole Process

So, how long does a building permit take in Miami? The City of Miami estimates about 14 business days for a first review cycle on a standard application, while unincorporated Miami-Dade County estimates 24 hours to 10 business days per review cycle. Eligible small residential jobs may even qualify for same-day express review. But those figures are review estimates. Your true timeline depends on how complete your application is, how many correction rounds you need, and whether outside approvals are involved.

The best strategy is simple: confirm your jurisdiction, submit a clean package, pay fees right away, track every update, and respond to comments quickly. That approach protects your schedule and your sanity.

Ready to take the guesswork out of your next permit? Get a free quote and let our team handle the filing, tracking, and revisions so your project keeps moving.

FAQs

How long does a building permit take in the City of Miami?

The City of Miami estimates about 14 business days for the first review cycle of a standard building permit, starting once your application is accepted into ePlan review. That is a first-cycle estimate, so corrections, extra review rounds, and fees can add time before you actually pull the permit.

How long does Miami-Dade County take to review building plans?

For unincorporated Miami-Dade County, initial plan review typically runs 24 hours to 10 business days, depending on permit type and project complexity. If you resubmit corrections, expect another 24 hours to 10 business days, and remember that plans are not reviewed until required upfront fees are paid.

Can I get a same-day building permit in Miami?

Possibly! Eligible small residential projects in the City of Miami may qualify for Homeowner's Express Review, and applications generally need to be in by 10 a.m. Eligibility, complete documents, and resubmission cutoffs apply, and some applications get moved to regular review.

How can I check the status of a Miami building permit application?

City of Miami applicants can track status, comments, and discipline-level progress in iBuild and ProjectDox. County applicants can use the Plans Status and Application Submittal Portal with their process number, so you always know where your file stands.

Is the permit timeline different in Miami Beach or Coral Gables?

Yes, it can be. Each municipality in Miami-Dade County has its own building official and permitting process, so the City of Miami's 14-day estimate does not automatically apply. Always confirm the jurisdiction for your address and check that building department's current procedures.

Need this handled?

We do this work every day across all 67 Florida counties. Call (866) 314-6931 and we will tell you what your situation actually requires — including when you do not need us.

Related services

Permit Facilitation & Filing

You have a crew scheduled, a client asking for dates, and a permit sitting somewhere in a queue you cannot see. We file it, w…

See the service

Plan Review Coordination

A permit in plan review is not one queue. On a commercial project it can be six queues, each with its own reviewer, its own c…